According to the ministry, 3 substations, 92 transformer substations and 273 km of power lines (4,963 electrical towers) were repaired and put into operation.
“As a result, stable energy supply was established for all 7,987 households, which suffered from disruption as a result of the flood,” the press service said.
Yesterday, it was reported that out of 12 settlements affected by the flood, 10 were fully provided with a stable supply of electricity. The completion of work was planned for May 18.