Emergency shutdown eliminated at Turakurgan TPP, the station operating at full capacity

POLITICS 11:57 / 21.11.2020 915

According to the Ministry of Energy, the rescue team had fixed the damage and ensured the full operation of units 1 and 2 of the TPP and at the moment, the station is operating at its installed capacity.

Also, for the needs of consumers, Unit 1 at the Takhiatash TPP as well as Unit 2 at the Talimarjan TPP have been launched.