EPSILON (EDC): Getting ready for the commissioning of “Mubarek – Zirabulak” pipeline string I

BUSINESS 17:43 / 03.11.2020 403

EDC completed installation and welding works to repair damaged sections of “Mubarek – Zirabulak” (“BGBA-TBA”) gas pipeline (50th–78th km). Pneumatic testing of pipeline string I is in progress using three mobile nitrogen units

At the same time, modernization and reconstruction of numerous main gas pipeline sections is underway, including construction of “Akhangaran – Pungan” pipeline looping (25 km) and branch line from the 338th km to “Yangiyer CS – Shirin GDS” (4.7 km), and repairs of “Mubarek – Zirabulak” (“BGBA-TBA”) strings II and III, “DBST”, “Kelif – Mubarek” and “BGBA-TBA-A” main pipeline sections (25.8 km).

All works fully comply with relevant sanitary-epidemiological and environmental requirements.

Epsilon Press Office

More news: