Construction of “Chigil CP – Mubarek GPP” dual-string pipeline with a design length of 110 km continues in cooperation with Uzbekneftegaz.
Total as of February 15:
- 152,400 t of pipes shipped;
- 143,300 t of pipes delivered;
- 191.7 km of trenches dug;
- 228.3 km of pipes welded;
- 127.9 km laid.
Epsilon Development Company (EDC) Press Office