Round-the-clock construction of “Chigil CP – Mubarek GPP” gas pipeline continues.
Total for February 3:
- 145,400 t of pipes shipped;
- 111,100 t of pipes arrived;
- 183.3 km of trenches dug;
- 223.6 km of pipes welded into a string;
- 127.6 km laid.
Epsilon Development Company (EDC) Press Office