In an effort to ensure steady supply of natural gas to the population, the company continues round-the-clock construction of “Chigil CP – Mubarek GPP” dual string pipeline with a design length of 110 km.
Total, as of January 30:
- 140,100 t of pipes shipped;
- 98,800 t of pipes arrived;
- 170.8 km of trenches dug;
- 220.2 km of pipes welded;
- 127.1 km laid.
Epsilon Development Company (EDC) Press Office