Round-the-clock construction of “Chigil CP – Mubarek GPP” pipeline continues.
Total for January 25:
- 127,900 t of pipes shipped;
- 87,400 t of pipes arrived;
- 159.9 km of trenches dug;
- 214.1 km of pipes welded;
- 126.3 km laid.
EPSILON Press Office
Round-the-clock construction of “Chigil CP – Mubarek GPP” pipeline continues.
Total for January 25:
EPSILON Press Office