On January 22, after workover and special treatment of Devkhona-6 wet well, the company obtained a production rate of 150,000 m3 of gas per day.
Construction of “Chigil CP – Mubarek GPP” pipeline is in progress. The works are being carried out in cooperation with Uzbekneftegaz.
Total for January 22:
- 122,400 t of pipes shipped;
- 79,500 t of pipes arrived;
- 154.8 km of trenches dug;
- 207.7 km of pipes welded into a string;
- 126.3 km laid.
EPSILON Press Office