“Chigil CP – Mubarek GPP” pipeline construction continues around the clock in cooperation with Uzbekneftegaz.
Completed works (as of January 20):
- 98,400 t of pipes shipped;
- 75,100 t of pipes arrived;
- 148.2 km of trenches dug;
- 201.7 km of pipes welded;
- 123 km laid.
EPSILON Press Office