Round-the-clock construction of “Chigil CP – Mubarek GPP” pipeline continues in an effort to increase gas transportation capacity of Kashkadarya region.
Total for January 19:
- 98,400 t of pipes shipped;
- 75,100 t of pipes arrived;
- 147.1 km of trenches dug;
- 198.8 km of pipes welded into a string;
- 122.7 km laid.