On January 15, after hydraulic fracturing at Khojiqazgan–52 and Kulbishkek-47 wells, their total daily flow rate reached 165,000 m³ of gas.
The production rate of Khojiqazgan-52 well increased from 40,000 to 85,000 m³ of gas per day.
The flow rate of Kulbishkek-47 well increased from 32,000 to 80,000 m³ of gas per day.
Despite weather conditions, round-the-clock construction of “Chigil CP – Mubarek GPP” gas pipeline continues.
Total for January 15:
- 91,000 t of pipes shipped;
- 70,000 t of pipes arrived;
- 136.0 km of trenches dug;
- 182.6 km of pipes welded;
- 120.2 km laid.
EPSILON Press Office