On January 13, following hydraulic fracturing, the flow rate of Kulbishkek-37 well reached 70,000 m³ of natural gas per day. These operations are carried out in cooperation with Uzbekneftegaz.
At the same time, the companies are developing gas transportation infrastructure. Round-the-clock construction of “Chigil CP – Mubarek GPP” continues.
Total for January 13:
- 91,000 t of pipes shipped;
- 69,200 t of pipes arrived;
- 128 km of trenches dug;
- 174.3 km of pipes welded;
- 119.6 km laid.
EPSILON Press Office