On January 9, after hydraulic fracturing at Doya Khatun–79 well, its daily flow rate increased from 38,000 to 85,000 m3 of gas.
Round-the-clock construction of “Chigil CP – Mubarek GPP” gas pipeline continues.
Total for January 9:
- 81,400 t of pipes shipped;
- 60,200 t of pipes arrived;
- 118.6 km of trenches dug;
- 156.7 km of pipes welded into a string;
- 117.5 km laid.
EPSILON Press Office