On January 8, following hydraulic fracturing at three wells of Doya Khatun field, their total daily flow rate reached 280,000 m³ of gas.
The flow rate of Doya Khatun-6 well increased from 0 to 80,000 m³ of gas per day.
The production rate of Doya Khatun-17 well increased from 60,000 to 100,000 m³ of gas per day.
The daily flow rate of Doya Khatun-58 well increased from 55,000 to 100,000 m³ of gas.
Construction of “Chigil CP – Mubarek GPP” gas pipeline continues.
As of January 8:
- 80,000 t of pipes shipped;
- 55,800 t of pipes arrived;
- 118.6 km of trenches dug;
- 152.9 km of pipes welded;
- 117.5 km laid.
EPSILON Press Office