On December 27, after fracking, the total daily flow rate of Doya Khatun-29 and Doya Khatun-73 wells reached 200,000 m³ of gas.
The production rate of Doya Khatun-29 well increased from 23,000 to 80,000 m³ of gas per day.
Round-the-clock construction of pipelines is underway to increase gas transmission network capacity in Kashkadarya region: “Tandircha CP – Shurtanneftegaz” (45 km) and “Chigil CP – Mubarek GPP” (110 km).
Total for December 27:
- 62,500 t of pipes shipped;
- 37,500 t of pipes arrived;
- 117.8 km of trenches dug;
- 133.3 km of pipes welded into a string;
- 109.4 km laid.
EPSILON Press Office