On December 26, following hydraulic fracturing, the total daily flow rate of Doya Khatun-16 and Doya Khatun-18 wells reached 200,000 m³ of gas.
The daily production rate of Doya Khatun-16 well increased from 60,000 to 100,000 m³ of gas.
The daily flow rate of Doya Khatun-18 increased from 50,000 to 100,000 m³ of gas.
On the same day, after successful pneumatic testing, the new 8-km-long “Talimarjon CP – Shurtanneftegaz” pipeline started transporting natural gas.
Round-the-clock construction of two gas pipelines continues: “CP Tandircha – Shurtanneftegaz” (45 km) and “Chigil CP – Mubarek GPP” (110 km).
Total for December 26:
- 62,500 t of pipes shipped;
- 37,500 t of pipes arrived;
- 116.4 km of trenched dug;
- 131.6 km of pipes welded;
- 99.9 km laid.
EPSILON Press Office