Construction of three pipelines is in progress to increase gas transmission network capacity in Kashkadarya region: “Tandircha CP – Shurtanneftegaz” (45 km), “Chigil CP – Mubarek GPP” (110 km), “Talimarjon CP – Shurtanneftegaz” (8 km).
Total for December 25:
- 62,500 t of pipes shipped;
- 36,600 t of pipes arrived;
- 107 km of trenches dug;
- 129.7 km of pipes welded;
- 89.5 km laid.