EPSILON: Intensifying expansion of gas pipeline network in Kashkadarya in cooperation with Uzbekneftegaz

BUSINESS 17:57 / 25.12.2019 374

Construction of three pipelines is in progress to increase gas transmission network capacity in Kashkadarya region: “Tandircha CP – Shurtanneftegaz” (45 km), “Chigil CP – Mubarek GPP” (110 km), “Talimarjon CP – Shurtanneftegaz” (8 km).

Total for December 25:

  • 62,500 t of pipes shipped;
  • 36,600 t of pipes arrived;
  • 107 km of trenches dug;
  • 129.7 km of pipes welded;
  • 89.5 km laid.

EPSILON Press Office

More news: