Successful partnership results in increased production of natural gas to supply the population during the winter period.
After fracking at Khojiqazgan-30 and Doya Khatun-30 wells, their total daily flow rate reached 190,000 m³ of gas.
The production rate of Khojiqazgan-30 increased from 64,000 to 110,000 m³ of gas per day.
The flow rate of Doya Khatun-30 well increased from 39,000 to 80,000 m³ of gas per day.
Round-the-clock construction of three gas pipelines is underway:
• “Tandircha CP – Shurtanneftegaz” (45 km);
• “Chigil CP – Mubarek GPP” (110 km);
• “Talimarjon CP – Shurtanneftegaz” (8 km).
Total for December 24:
• 60,500 t of pipes shipped;
• 34,400 t of pipes arrived;
• 101.9 km of trenches dug;
• 127.2 km of pipes welded into a string;
• 83.8 km laid.
EPSILON Press Office