On December 23, following hydraulic fracturing at Khojiqazgan-36 and Doya Khatun-71 wells, their total daily flow rate reached 210,000 m³ of natural gas.
The production rate of Khojiqazgan-36 well increased from 60,000 to 110,000 m³ of gas per day.
The flow rate of Doya Khatun-71 well increased from 52,000 to 100,000 m³ of gas per day.
Round-the-clock construction of three gas pipelines continues:
- “Tandircha CP – Shurtanneftegaz” (45 km);
- “Chigil CP – Mubarek GPP” (110 km);
- “Talimarjon CP – Shurtanneftegaz” (8 km).
Total for December 23:
- 58,900 t of pipes shipped;
- 34,000 t of pipes arrived;
- 100.5 km of trenches dug;
- 126 km of pipes welded;
- 78.7 km laid.
EPSILON Press Office