EPSILON: Increasing production of hydrocarbons and developing gas transportation infrastructure in Kashkadarya in cooperation with Uzbekneftegaz

BUSINESS 18:05 / 22.12.2019 363

On December 22, after fracking at Kulbishkek-36 and Doya Khatun-75 wells, their daily flow rate reached 170,000 m³ of gas.

The daily production rate of Kulbishkek-36 well increased from 0 to 50,000 m³ of gas.

The daily production rate of Doya Khatun-75 well increased from 70,000 to 120,000 m³ of gas.

Round-the-clock construction of gas pipelines continues:

  • “Tandircha CP - Shurtanneftegaz” (45 km); 
  • “Chigil CP - Mubarek GPP” (110 km); 
  • “Talimarjon CP - Shurtanneftegaz” (8 km).

Total for December 22:  

  • 52,800 t of pipes shipped;
  • 33,600 t of pipes arrived;
  • 96.7 km of trenches dug;
  • 124.1 km of pipes welded;
  • 77.4 km laid.

EPSILON Press Office