Round-the-clock construction of pipelines continues to increase gas transportation capacity in Kashkadarya region:“Tandircha CP – Shurtanneftegaz” (45 km), “Chigil CP – Mubarek GPP” (110 km), “Talimarjon CP – Shurtanneftegaz” (8 km).
Total for December 21:
- 50,800 t of pipes shipped;
- 31,700 t of pipes arrived;
- 95.7 km of trenches dug;
- 121.9 km of pipes welded into a string;
- 77.4 km laid.