On December 19, following successful fracking at Qumli-22 and Kulbishkek-48 wells, their total daily flow rate reached 160,000 m³ of gas.
The production rate of Qumli-22 well increased from 0 to 60,000 m³ of gas per day.
The flow rate of Kulbishkek-48 well increased from 40,000 to 100,000 m³ of gas per day.
Round-the-clock construction of gas pipelines continues:
- “Tandircha CP – Shurtanneftegaz” (45 km);
- “Chigil CP – Mubarek GPP” (110 km);
- “Talimarjon CP – Shurtanneftegaz” (8 km).
Total for December 19:
- 46,200 t of pipes shipped;
- 29,700 t of pipes arrived;
- 91.3 km of trenches dug;
- 117.2 km of pipes welded into a string;
- 75.9 km laid.
EPSILON Press Office