Round-the-clock construction of three gas pipelines continues: “Tandircha CP – Shurtanneftegaz” (45 km), “Chigil CP – Mubarek GPP” (110 km), “Talimarjon CP – Shurtanneftegaz” (8 km).
Total for December 18:
- 46,200 t of pipes shipped;
- 29,700 t of pipes arrived;
- 90.8 km of trenches dug;
- 114.7 km of pipes welded;
- 74.3 km laid.