Pneumatic testing of 67 km long “Nazarkuduk CP – Shurtanneftegaz” gas pipeline is in progress. Round-the-clock construction of two pipelines continues: “Tandircha CP – Shurtanneftegaz” (45 km) and “Chigil CP – Mubarek GPP” (110 km).
Total for December 13:
- 36,800 t of pipes shipped;
- 24,600 t of pipes arrived;
- 70.9 km of trenches dug;
- 98.4 km of pipes welded into a string;
- 59.4 km laid.