EPSILON: Developing gas pipeline infrastructure in cooperation with Uzbekneftegaz

BUSINESS 19:23 / 13.12.2019 1197

Pneumatic testing of 67 km long “Nazarkuduk CP – Shurtanneftegaz” gas pipeline is in progress. Round-the-clock construction of two pipelines continues: “Tandircha CP – Shurtanneftegaz” (45 km) and “Chigil CP – Mubarek GPP” (110 km).

Total for December 13:

  • 36,800 t of pipes shipped;
  • 24,600 t of pipes arrived;
  • 70.9 km of trenches dug;
  • 98.4 km of pipes welded into a string;
  • 59.4 km laid.

EPSILON Press Office