EPSILON: Developing gas pipeline infrastructure in Kashkadarya region in cooperation with Uzbekneftegaz

BUSINESS 18:48 / 11.12.2019 496

Сonstruction of three gas pipelines continues: “Nazarkuduk collecting point – Shurtanneftegaz” (67 km), “Tandircha CP – Shurtanneftegaz” (45 km) and “Chigil CP – Mubarek gas processing plant” (110 km). Pneumatic testing (stage one) of “Nazarkuduk CP – Shurtanneftegaz” pipeline is in progress.

The speed of round-the-clock construction is, on average, 4 km per day.

Total for December 11:
•  36,000 t of pipes shipped;
•  23,600 t of pipes arrived;
•  62.4 km of trenches dug;
•  94.4 km of pipes welded;
•  51.5 km laid.

Epsilon Press Office