Round-the-clock construction of three gas pipelines – “Nazarkuduk CP-Shurtanneftegaz” (67 km), “Tandircha CP-Shurtanneftegaz” (45 km) and “Chigil CP-Mubarek GPP” (110 km) – continues. The first stage of pneumatic testing of “Nazarkuduk CP-Shurtanneftegas” pipeline is in progress.
Over the past day, 800 t of pipes were shipped and 1,400 t were delivered; 2.4 km of trenches were dug, 5.9 km of pipes were welded into a string and 6 km were laid.
The average pipeline construction speed is 4 km per day.
Total for December 9:
- 33,300 t of pipes shipped;
- 21,400 t of pipes arrived;
- 60.3 km of trenches dug;
- 86.8 km of pipes welded;
- 37.1 km laid.
EPSILON Press Office