Construction of new pipelines is underway in an effort to increase gas transportation capacity and supply the population with natural gas.
Pipeline construction continues:
- “Nazarkuduk CP – Shurtanneftegaz” (67 km);
- “Tandricha CP – Shurtanneftegaz” (45 km);
- “Chigil CP – Mubarek GPP” (110 km).
Total for December 7:
- 31,700 t of pipes shipped;
- 20,000 t of pipes arrived;
- 57 km of trenches dug;
- 72.1 km of pipes welded into a string;
- 15.5 km laid.
EPSILON Press Office