Over the past day, 2,400 t of pipes were shipped, 2.7 km of trenches were dug and 1,300 m of pipes were laid. In addition, 6.6 km of pipes were transported to the location of “Tandircha CP – Shurtanneftegaz” and 700 m – to “Chigil CP – Mubarek GPP”.
The first string of “Nazarkuduk CP – Shurtanneftegaz” pipeline is almost ready. Preparation for pneumatic testing is underway. The company began construction of “Tandircha CP – Shurtanneftegaz” and “Chigil CP – Mubarek GPP” gas pipelines.
As of December 03, 26,700 t of pipes were shipped and 17,300 t were delivered; 52.1 km of trenches were dug, 61.3 km of pipes were welded and 9.9 km were laid.
Round-the-clock works are ahead of schedule.
Epsilon will keep updating the readers on the progress of its undertakings.