On November 29, after hydraulic fracturing, the daily production rate of two wells at Kukdumalok field increased from 9.8 to 35 t of oil.
On November 28-29, fracking operations were conducted at three wells of Koratepa, Kirkchashma and Chulkuvar fields. Industrial flow of gas is expected.
Pipeline construction continues
Over the past day, 600 t (2.2 km) of pipes were shipped and 1,400 t (6.4 km) were received; 1,400 m of trenches were dug, 3.5 km of pipes were welded into a string and 600 m were laid.
As of November 29, 22,600 t (129.6 km) of pipes were shipped and 15,900 t (95.0 km) were delivered; 37.2 km of trenches were dug, 58.0 km of pipes were welded and 7.5 km were laid.
The company will keep informing the readers about its undertakings.
EPSILON Press Office