On November 28, after completion of drilling and hydraulic fracturing, the daily flow rate of new Chigil–5 well is 300,000 m³. All produced gas will be routed to the domestic market.
Pipeline construction
As of November 28, 22,000 t (127.4 km) of pipes were shipped and 14,500 t (88.6 km) were delivered; 35.8 km of trenches were dug, 54.5 km of pipes were welded into a string and 6.9 km were laid.
Over the past day, 400 t (1.6 km) of pipes were shipped and 2,400 t (14.9 km) were delivered; 2 km of trenches were dug, 3.6 km of pipes were welded and 700 m were laid.
The company will continue reporting on its progress.