On November 25-26, fracking operations were conducted at three wells of Koratepa, Kirkchashma and Bokhoriston fields. The company expects industrial inflow of gas.
Construction of pipelines:
As of November 26, 20,900 t (122.6 km) of pipes were shipped and 12,100 t (73.7 km) were delivered; 31.1 km of trenches were dug, 47.8 km of pipes were welded into a string and 5.5 km were laid.
Over the past day, 1,800 t (9 km) of pipes were shipped, 200 t (800 m) were delivered, 1,000 m of trenches were dug, 3.5 km of pipes were welded and 700 m were laid.
All produced gas is routed to the domestic market to cover the needs of Uzbekistan’s population.
Epsilon will continue informing the readers on its undertakings.