On November 21-22, after hydraulic fracturing, gas inflow was obtained from three wells of Janubiy Tandircha and Samantepe fields. The total daily flow rate increased from 287,000 to 490,000 m³.

The flow rate of Janubiy Tandircha–81 reached 200,000 m³ per day.

The production rate of Janubiy Tandircha–49 reached 150,000 m³ per day.

The flow rate of Samantepe–84 reached 140,000 m³ per day.

Construction of gas pipelines continues. 

Over the past day, 1,800 t (9.5 km) of pipes were shipped and 1,900 t (12.1 km) were delivered; 1,600 m of trenches were dug and 4.1 km of pipes were welded into a string.

As of November 22, 18,000 t (107.6 km) of pipes were shipped and 11,900 t (72.9 km) were delivered; 21.6 km of trenches were dug, 34.4 km of pipes were welded and 3.5 km of pipes were laid.

The construction will be completed on December 6, 2019.