Epsilon in cooperation with Uzbekneftegaz increases production of hydrocarbons

BUSINESS 12:40 / 21.11.2019 878

On November 20-21, following hydraulic fracturing, gas inflow was obtained from three wells of Janubiy Tandircha field. The total daily production rate increased from 350,000 to 550,000 m³.

After fracking, the daily flow rate of Janubiy Tandircha-27 reached 180,000 m³ of gas.

After fracking at Janubiy Tandircha-57, its daily production rate increased to 200,000 m³ of gas.

After fracking at Janubiy Tandircha-32, its daily flow rate reached 170,000 m³ of gas.

Construction of gas pipelines continues

As of November 21, 16,200 t (98.1 km) of pipes were shipped and 10,000 t (60.8 km) were delivered; 20 km of trenches were dug, 30.3 km of pipes were welded into a string and 3.5 km of pipes were laid.

The construction will be completed on December 6, 2019.

Epsilon will continue updating the readers on its undertakings.

EPSILON Press Office