As of November 19, 13,700 t (84.2 km) of pipes were shipped and 9,900 t (60.5 km) were delivered; 17.3 km of trenches were dug, 22.8 km of pipes were welded into a sting and 3.1 km of pipes were laid.
Over the past day, 600 t (3.5 km) of pipes were shipped and 700 t (4.5 km) were delivered; 900 m of trenches were dug and 3.2 km of pipes were welded. The company intends to construct 4 km of pipelines per day, starting from November 21, 2019.
Epsilon will continue informing the readers on the progress of construction.