As of November 16, 2019, 1.4 km of pipes were laid, 13.6 km of pipes were welded into a string and 14.4 km of trenches were dug; 9,200 t (56 km) of pipes arrived and 11,700 t (72.2 km) were shipped.
Over the past day, 2.4 km of pipes were welded, 800 m of trenches were dug and 1,300 t (8 km) of pipes were delivered.
To ensure steady supply of natural gas during the autumn-winter period, the companies began construction of two double-line pipelines: “Nazarkuduk AP – Shurtanneftegaz” (67 km) and “Chigil AP – Mubarek GPP” (110 km). These pipelines will be transporting gas to the processing facilities.
Construction of the first line of “Nazarkuduk AP – Shurtanneftegaz” pipeline is expected to be completed by December 10, 2019.
Epsilon will continue informing the readers about the progress of construction.
Epsilon Press Office