As of November 15, 2019, 1.4 km of pipes were laid, 11.2 km were welded and 13.6 km of trenches were dug; 7,900 t of pipes (48 km) arrived and 11,700 t (72.2 km) were shipped.
Over the past day, additional 1.8 km of pipes were welded and 1.6 km of trenches were dug.
To supply the population with natural gas during the autumn-winter period, the companies started construction of two double-line pipelines: “Nazarkuduk AP – Shurtanneftegaz” (67 km) and “Chigil AP – Mubarek GPP” (110 km). These will be transporting gas to the processing facilities.
Epsilon will keep the readers updated on the progress of construction.
Epsilon Press Office