As of November 14, 1.4 km of pipes were laid, 9.4 km of pipes were welded and 12 km of trenches were dug; 7,900 t of pipes (48 km) arrived and 11,700 t of pipes (72.2 km) were shipped.
Earlier, Epsilon reported that construction of two double-line pipelines – «Nararkuduk assembly point – Shurtanneftegaz» (67 km) and «Chigil assembly point – Mubarek gas processing plant» (110 km) – is underway. They will be used for transportation of extracted gas to the processing facilities with the aim of supplying the population during the autumn-winter period.
The company will continue informing readers on its progress.
Epsilon Press Office