ERIELL Group actively increases hydrocarbon production

BUSINESS 17:17 / 01.11.2019 1288

ERIELL Group informed about the structure of fields of the JSC Uzbekneftegaz within the framework of the “Program of measures to increase hydrocarbon production for 2017-2021”.

In the Mubarek district, commissioning of the well No. 317 at the “Dengizkul” field was successfully completed. Construction of a loop gas pipeline with a diameter of 114×9 mm and a length of 550 meters has been accomplished. The well is connected to an existing input thread block at the “Dengizkul” field.

Well No. 12 of the “Oydin” field was successfully commissioned in the Shurtan area. Construction of a loop gas pipeline with a diameter of 114×9 mm and a length of 2,410 meters has been completed. The well is connected to the “Nomozboy-Oydin” gas pre-treatment unit.

More news: